Georgia Development of Regional Impact (DRI) Review Threshold (GA)

Tracked preemption from the Georgia overlay bundle.

Overview

Effective
1989-07-01
Sunset
Authority
state
Scope
state:GA

Trigger predicate

When this evaluates true for a parcel, the law's preempted fields take precedence over base zoning.

OR
  • project.residential_units 400
  • project.office_sqft 400000
  • project.commercial_sqft 300000
  • project.industrial_sqft 1000000
  • project.hotel_rooms 400
  • project.mixed_use_acres 100

Preempted fields

2 fields on the base district schema are rewritten when the trigger fires.

FieldOpValueNote
review_typeoverriderequires_regional_commission_dri_reviewLocal zoning approval cannot proceed until the Regional Commission (or ARC for metro Atlanta) completes the DRI review process; thresholds are tier-adjusted by jurisdiction size and regional commission
review_timeline.dri_minimum_review_daysfloor_at50DRI review process typically requires 50+ calendar days from initial DRI form submission to final report

Citation

Authority source
O.C.G.A. §50-8-7.1(b)(2); DCA Rules Chapter 110-12-3 (DRI Procedures)
§ DCA Rules 110-12-3; ARC reviews for the 11-county metro Atlanta region
https://www.dca.ga.gov/local-government-assistance/planning/development-regional-impact-dri

Research notes

DRI review is procedural — the Regional Commission (RC) or Atlanta Regional Commission (ARC for the metro Atlanta region) issues a non-binding finding on regional impacts (transportation, infrastructure, environment, housing). Local government may still approve a project receiving an unfavorable DRI finding, but doing so foregoes future state DCA Qualified Local Government (QLG) status and grant eligibility. Thresholds vary by RC tier; values shown are typical ARC metro thresholds. is_metro_atlanta city attribute drives ARC vs. other RC review path. Verify thresholds against current DCA rules for the applicable RC.