Oklahoma Wind Energy Development Act — Setbacks, Decommissioning, Notice (OK)

Tracked preemption from the Oklahoma overlay bundle.

Overview

Effective
2010-11-01
Sunset
Authority
state
Scope
state:OK

Trigger predicate

When this evaluates true for a parcel, the law's preempted fields take precedence over base zoning.

project.use_type == utility_scale_wind_turbine

Preempted fields

4 fields on the base district schema are rewritten when the trigger fires.

FieldOpValueNote
project.wind_turbine_setback_from_dwelling_ftfloor_at1.1§160.20 et seq.: minimum setback from a nonparticipating residence is the greater of 1.1× the total turbine height OR the manufacturer's recommended minimum. (Multiplier — final feet vary by turbine height.)
project.wind_turbine_setback_from_property_line_ftfloor_at1.1Minimum setback from a nonparticipating property line is the greater of 1.1× total height OR manufacturer's recommended minimum
project.decommissioning_financial_assurance_requiredrequireTrue§160.24: financial assurance for decommissioning must be posted before commercial operation
review_typerequireocc_pre_construction_notice_and_municipal_jlus_checkOCC pre-construction notice required; siting near military airfields and FAA radar coverage triggers DoD Siting Clearinghouse review

Citation

Authority source
Okla. Stat. tit. 17 §§160.20 through 160.24 (Oklahoma Wind Energy Development Act); administered in part by the Oklahoma Corporation Commission
§ §§160.20 et seq.
https://law.justia.com/codes/oklahoma/title-17/

Research notes

Oklahoma is the #3 wind-power state by installed capacity; SCOOP/STACK landowners frequently host both oil/gas (§52-137) and utility-scale wind on the same surface estate. The 2017 'Wind Catcher' project (Invenergy/AEP/PSO) was a marquee proposed Panhandle build that was withdrawn; subsequent multi-gigawatt builds continue across Beaver, Texas, Cimarron, Woodward, Dewey, Custer, Caddo, Roger Mills, Harper, Ellis Cos. Federal conflict check applies — DoD Mission Compatibility Evaluation and FAA Part 77 / Form 7460-1 are mandatory parallel reviews; setbacks may be enlarged by military mission-area constraints around Tinker, Vance, Altus, and Fort Sill.