Washington SB 5290 — Local Permit Review Timelines (WA)

Tracked preemption from the Washington overlay bundle.

Overview

Effective
2024-01-01
Sunset
Authority
state
Scope
state:WA

Trigger predicate

When this evaluates true for a parcel, the law's preempted fields take precedence over base zoning.

city.growth_management_act_tier attribute is present

Preempted fields

4 fields on the base district schema are rewritten when the trigger fires.

FieldOpValueNote
permit_review_max_days_type1cap_at65Type 1 (admin, no public notice): 65 calendar days
permit_review_max_days_type2cap_at100Type 2 (admin with notice): 100 calendar days
permit_review_max_days_type3cap_at170Type 3 (hearing examiner / quasi-judicial): 170 calendar days
permit_review_max_days_type4cap_at170Type 4 (legislative project): 170 calendar days

Citation

Authority source
WA SB 5290 (2023) / RCW 36.70B.080
§ RCW 36.70B.080
https://app.leg.wa.gov/billsummary?BillNumber=5290&Year=2023

Research notes

Statutory maximum review timelines for local project permit review. Running afoul triggers state-mandated permit fee refunds on a graduated scale (10%-100% of fees). Applies to cities and counties planning under GMA.